Answer: B
Answer Explanation: We need Substitute rule in 'document approval' task to achieve this.
During a Procurement Contract implementation, a customer would like to set up approvals for procurement contract documents. The customer has four departments and any contract needs to be approved by all the four department users. Identify the configuration to fulfill this requirement ?
Options:
A. Set up employee supervisor hierarchy for all four department users and add them to an approval group.
B. Set up one approval group and include the four department users with voting regime as first responder wins.
C. Set up user group for the four departments and set up individual rules for the four department users. D. Set up one approval group and include the four department users with voting regime as consensus.
Answer: D
Answer Explanation: Preapproval Header Consensus Approvals are routed in parallel for this participant. This participant is more commonly used in conjunction with approval groups. This participant requires approval from all approvers.
During the implementation, your customer wants to understand
the key features of the two stage Request For Quotation (RFQ) available in
Oracle Sourcing Cloud. Identify three features of the two-stage RFQ. (Choose
three.)
Options:
A. Response
Visibility Open
B. Two stage
Evaluation
C. Technical and
Commercial Evaluation
D. Response Visibility is always Sealed E. Open Auctions F.
Response Visibility Blind
Answer: B,C,D
Answer Explanation: The two-stage RFQ process involves the submission by the suppliers of a technical quote and a commercial quote. The technical quotes are opened and evaluated first to determine a list of qualified suppliers, and only then are the commercial quotes of the qualified suppliers opened and evaluated. Two Stage RFQ Ensure impartial judgment of supplier responses in markets that require technical and commercial evaluation of proposals to be done independently. While suppliers submit their responses as a single bid package, category managers first analyze the technical merits of the proposal while the commercial aspects of the bid remain sealed. Commercial details of bids that pass the technical evaluation are disclosed in the second evaluation phase, while the details of failed bids remain sealed. Category managers enter surrogate responses on behalf of suppliers by submitting the technical terms of the proposal during the first stage of the negotiation, and only entering the commercial terms if the first stage evaluation is successful